Blackwater Bridge Replacement with Outflow Stormdrain Culvert
Federal contribution
$50,000
Federal share21%
of $232.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of McKellar
- Construction start
- Sep 19, 2017(actual)
- Construction end
- Oct 17, 2017(actual)
Against the original forecast
- Construction start16 months lateforecast Jun 1, 2016
- Construction end5 months earlyforecast Mar 31, 2018
Also in McKellar