Establish an industrial park
Federal contribution
$1.4M
$1,386,378
Federal share30%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2005
20062007200820092010
Built
Approved 3 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of New Richmond
- Construction start
- Nov 7, 2005(actual)
- Construction end
- Mar 25, 2010(actual)