Water Systems Upgrade
Federal contribution
$522,250
Federal share40%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- New Richmond
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Dec 8, 2021(actual)
Against the original forecast
- Construction end7 months earlyforecast Jun 30, 2022