Program for the renewal of drinking water and wastewater pipes
Federal contribution
$227,758
Federal share31%
of $735.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 13, 2009
20102011
Built
Approved 3 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of New Richmond
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
Also in New Richmond
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37014 in the federal list. How to read these figures.