Back to projects

Building a reception chalet and improving snowmaking system

Rouyn-Noranda, Quebec

completeSportMRIF
Federal contribution
$624,627
Federal share28%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 16, 2006
200620072008
Built

Approved 6 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Nov 21, 2005(actual)
Construction end
Oct 31, 2008(actual)

Also in Rouyn-Noranda

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14168 in the federal list. How to read these figures.