Infrastructure Phase 3 St-Athanase sector

Saint-Jean-sur-Richelieu, Quebec

completeWastewaterMRIF
Federal contribution
$1.7M
$1,688,020
Federal share32%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 14, 2008
20092010
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Mar 20, 2008(actual)
Construction end
Feb 8, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Mar 1, 2008
  • Construction end10 months lateforecast Mar 31, 2009

Also in Saint-Jean-sur-Richelieu

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14351 in the federal list. How to read these figures.