Water Systems Upgrades
Saint-Jean-sur-Richelieu, Quebec
Federal contribution
$1.9M
$1,928,334
Federal share40%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023202420252026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Saint-Jean-sur-Richelieu
- Construction start
- May 3, 2021(actual)
- Construction end
- Jul 14, 2026(forecast)
Against the original forecast
- Construction start4 weeks lateforecast Apr 5, 2021
Also in Saint-Jean-sur-Richelieu
- Reconstruction of Gouin Bridge in Saint-Jean-sur-Richelieu$18.6M
- Program for the renewal of drinking water and wastewater pipes$2.0M
- Upgrade to Water Filtration Plant for Ibreville$1.9M
- Infrastructure Phase 3 St-Athanase sector$1.7M
- Construction of sewer and water systems in the Fleur de Lys sector$1.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56731 in the federal list. How to read these figures.