Back to projects

Construction of sewer and water systems in the Fleur de Lys sector

Saint-Jean-sur-Richelieu, Quebec

completeWastewaterCC
Federal contribution
$1.2M
$1,233,334
Federal share20%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.4 years before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Jun 1, 2010(actual)
Construction end
Jun 30, 2013(actual)

Against the original forecast

  • Construction end2.6 years lateforecast Nov 30, 2010

Also in Saint-Jean-sur-Richelieu

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36842 in the federal list. How to read these figures.