Back to projects

Trois-Rivières on Saint-Laurent

Trois-Rivières, Quebec

completeRecreationMRIF
Federal contribution
$6.8M
$6,753,918
Federal share33%

of $20.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 2, 2008
2009201020112012
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Trois-Rivières
Construction start
Dec 1, 2008(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction start10 months earlyforecast Oct 1, 2009

Also in Trois-Rivières

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14355 in the federal list. How to read these figures.