Trois-Rivières Amphitheater
Federal contribution
$13.3M
$13,300,000
Federal share33%
of $40.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 3, 2009
ApprovedDec 23, 2009
2010201220142016
Built
Approved 6 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Trois-Rivières
- Construction start
- Apr 16, 2012(actual)
- Construction end
- Nov 25, 2016(actual)
Against the original forecast
- Construction end5 months lateforecast Jun 30, 2016
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32706 in the federal list. How to read these figures.