Expanding Storage Space at the Port of Trois-Rivières

Trois-Rivières, Quebec

completeMarineISF
Federal contribution
$3.9M
$3,925,818
Federal share45%

of $8.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedNov 2, 2009
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Mar 12, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Sep 28, 2009

Also in Trois-Rivières

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29325 in the federal list. How to read these figures.