Bring Saint-Philémon's drinking water water supply infrastructure up to standard
Federal contribution
$61,889
Federal share20%
of $303.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 6, 2006
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Saint-Philémon
- Construction start
- Sep 15, 2006(actual)
- Construction end
- Nov 30, 2006(actual)