Water Supply System at Massif du Sud
Federal contribution
$2.1M
$2,061,350
Federal share33%
of $6.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 28, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Saint-Philémon
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Oct 15, 2011(actual)
Also in Saint-Philémon