Back to projects

Water System Upgrades

Saint-Philémon, Quebec

completeWastewaterGIS
Federal contribution
$282,795
Federal share40%

of $707.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 13, 2022(actual)
Construction end
Nov 1, 2022(actual)

Also in Saint-Philémon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56702 in the federal list. How to read these figures.