Back to projects

Water Utility Upgrades

New Minas, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$145,704
Federal share33%

of $437.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2007
2007200820092010
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of New Minas
Construction start
Jan 22, 2007(actual)
Construction end
Jun 15, 2010(actual)

Against the original forecast

  • Construction start14 months lateforecast Nov 24, 2005
  • Construction end14 months lateforecast Mar 31, 2009

Also in New Minas