Highway 101 Granite Drive Interchange and Connector
Federal contribution
$7.5M
$7,457,852
Federal share49%
of $15.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 7, 2016
20172018
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Dec 14, 2016(actual)
- Construction end
- Nov 22, 2018(actual)
Against the original forecast
- Construction start6 weeks lateforecast Nov 1, 2016
- Construction end3 weeks lateforecast Oct 31, 2018
Also in New Minas
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46733 in the federal list. How to read these figures.