New Minas Water and Sewer Upgrade
Federal contribution
$277,519
Federal share33%
of $832.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
201020112012201320142015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of New Minas
- Construction start
- Apr 15, 2010(actual)
- Construction end
- Aug 18, 2015(actual)
Against the original forecast
- Construction start9 months lateforecast Jul 1, 2009
- Construction end5 weeks lateforecast Jul 15, 2015
Also in New Minas
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26289 in the federal list. How to read these figures.