Mahone Bay Water System Upgrade Phase 2

Mahone Bay, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$808,755
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 14, 2006
20072008200920102011
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Mahone Bay
Construction start
Jul 27, 2006(actual)
Construction end
Apr 22, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 24, 2005
  • Construction end13 months lateforecast Mar 31, 2010

Also in Mahone Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14561 in the federal list. How to read these figures.