Edgewater Street Shoreline Active Transportation Trail
Federal contribution
$893,522
Federal share60%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 6, 2025
today
20232024202520262027
BuiltForecast
Approved 2.2 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Mahone Bay
- Construction start
- Aug 15, 2025(actual)
- Construction end
- Nov 30, 2026(forecast)
Against the original forecast
- Construction start2.2 years lateforecast May 31, 2023
Also in Mahone Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64557 in the federal list. How to read these figures.