Graves Island Provincial Park Causeway Adaptation
Federal contribution
$1.0M
$1,000,000
Federal share50%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 20, 2023
today
20232024202520262027
BuiltForecast
Approved 16 months before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Nova Scotia Department of Natural Resources and Renewables
- Construction start
- Sep 1, 2026(forecast)
- Construction end
- Mar 31, 2027(forecast)
Also in Mahone Bay
- Town of Mahone Bay - Main Street West Water and Wastewater Rehabilitation$2.2M
- Mahone Bay Harbour's coastline$928.0K
- Edgewater Street Shoreline Active Transportation Trail$893.5K
- Mahone Bay Water System Upgrade Phase 2$808.8K
- Pleasant Street Water, Wastewater and Stormwater Seperation/Replacement$771.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62577 in the federal list. How to read these figures.