Tatamagouche Water Treatment Plant

Tatamagouche, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$779,731
Federal share33%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 29, 2006
20072008
Built

Approved 5 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 27, 2006(actual)
Construction end
May 2, 2008(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 24, 2005
  • Construction end11 months earlyforecast Mar 31, 2009