Willow Lodge - Facility Upgrades
Federal contribution
$134,528
Federal share80%
of $168.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Willow Lodge
- Construction start
- Sep 21, 2021(actual)
- Construction end
- Jun 13, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Mar 31, 2022
Also in Tatamagouche
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60436 in the federal list. How to read these figures.