Back to projects

Willow Lodge - Laundry Upgrade

Tatamagouche, Nova Scotia

completeHealthcare InfrastructureCVRIS
Federal contribution
$48,209
Federal share80%

of $60.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2021
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Willow Lodge
Construction start
Sep 21, 2021(actual)
Construction end
Sep 24, 2021(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2021
  • Construction end3 months earlyforecast Dec 31, 2021

Also in Tatamagouche