Water System Improvements
Federal contribution
$123,335
Federal share33%
of $370.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2007
20072008
Built
Approved 6 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Hillsborough
- Construction start
- Jan 23, 2007(actual)
- Construction end
- Sep 28, 2008(actual)
Against the original forecast
- Construction start3 months earlyforecast May 1, 2007
- Construction end11 months lateforecast Oct 31, 2007
Also in Hillsborough