Lift Station Upgrades
Federal contribution
$516,927
Federal share32%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2015
201620172018
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Hillsborough
- Construction start
- Mar 16, 2018(actual)
- Construction end
- Oct 3, 2018(actual)
Against the original forecast
- Construction start2 months earlyforecast May 16, 2018
- Construction end8 weeks earlyforecast Nov 30, 2018
Also in Hillsborough
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46058 in the federal list. How to read these figures.