Hillsborough Arena Upgrades - Phase 1

Hillsborough, New Brunswick

completeRecreationSCF
Federal contribution
$500,221
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2018
2019
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Hillsborough
Construction start
Apr 1, 2019(actual)
Construction end
Nov 1, 2019(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Apr 16, 2019
  • Construction end7 months earlyforecast Jun 1, 2020

Also in Hillsborough

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52381 in the federal list. How to read these figures.