Water Utility - Groundwater Supply

Bridgetown, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$1.1M
$1,076,261
Federal share33%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2007
20072008200920102011
Built

Approved 11 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Bridgetown
Construction start
Jul 27, 2006(actual)
Construction end
Apr 30, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 24, 2005
  • Construction end13 months lateforecast Mar 31, 2010

Also in Bridgetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14742 in the federal list. How to read these figures.