Back to projects

Purchase of two bus shelters for transit riders in Bridgewater, Nova Scotia

Bridgetown, Nova Scotia

completePublic TransitRTSF
Federal contribution
$32,160
Federal share80%

of $40.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 12, 2024
202420252026
Built

Approved 17 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Town of Bridgewater
Construction start
Jul 25, 2023(actual)
Construction end
Dec 31, 2025(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 30, 2023
  • Construction end9 months lateforecast Mar 31, 2025