Back to projects

Church Street Upgrade

Bridgetown, Nova Scotia

completeHighways and RoadsCC Top Up
Federal contribution
$291,041
Federal share33%

of $873.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Bridgetown
Construction start
Aug 3, 2009(actual)
Construction end
Jun 15, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2009
  • Construction end9 months lateforecast Aug 31, 2009

Also in Bridgetown