Water & Sewer - Redwood Road to Juniper Road / Sanitary Sewer Outfall

Springdale, Newfoundland and Labrador

completeWastewaterMRIF
Federal contribution
$204,704
Federal share33%

of $614.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20082010201220142016
Built

Approved 8.2 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Springdale
Construction start
Jan 8, 2008(actual)
Construction end
Oct 26, 2009(actual)

Against the original forecast

  • Construction start5 months earlyforecast Jun 1, 2008
  • Construction end14 months lateforecast Aug 31, 2008