Water & Sewer - Redwood Road to Juniper Road / Sanitary Sewer Outfall
Springdale, Newfoundland and Labrador
Federal contribution
$204,704
Federal share33%
of $614.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20082010201220142016
Built
Approved 8.2 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Springdale
- Construction start
- Jan 8, 2008(actual)
- Construction end
- Oct 26, 2009(actual)
Against the original forecast
- Construction start5 months earlyforecast Jun 1, 2008
- Construction end14 months lateforecast Aug 31, 2008
Also in Springdale
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14832 in the federal list. How to read these figures.