Main Street (Hemlock to Little Bay Road) Water, Sanitary Sewer and Storm Sewer Installation and Road Resurfacing
Springdale, Newfoundland and Labrador
Federal contribution
$609,467
Federal share40%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
20242025
BuiltForecast
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Springdale
- Construction start
- May 5, 2025(actual)
- Construction end
- Oct 31, 2025(forecast)
Also in Springdale
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67323 in the federal list. How to read these figures.