Valley Vista Seniors Home - Emergency Generator Replacement
Springdale, Newfoundland and Labrador
Federal contribution
$564,353
Federal share80%
of $705.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.6 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Aug 1, 2023(actual)
- Construction end
- May 31, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2023
- Construction end3 months lateforecast Feb 28, 2025
Also in Springdale
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64680 in the federal list. How to read these figures.