Water and Sewer Upgrade - Pinchmarsh Road

Fortune, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$136,354
Federal share33%

of $409.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.9 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Fortune
Construction start
May 22, 2009(actual)
Construction end
Mar 17, 2011(actual)

Against the original forecast

  • Construction end15 months lateforecast Dec 1, 2009

Also in Fortune

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14854 in the federal list. How to read these figures.