Arena Floor Replacement

Fortune, Newfoundland and Labrador

completeRecreationSCF
Federal contribution
$418,143
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
201720182019
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Fortune
Construction start
Apr 15, 2017(actual)
Construction end
May 28, 2019(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 1, 2017
  • Construction end5 months lateforecast Dec 31, 2018

Also in Fortune

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46745 in the federal list. How to read these figures.