Shoreline Erosion Control - Location 1

Fortune, Newfoundland and Labrador

completeDisaster MitigationGIS
Federal contribution
$425,552
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2024
20242025
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Fortune
Construction start
Feb 7, 2025(actual)
Construction end
Mar 20, 2025(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Mar 27, 2025
  • Construction end4 months earlyforecast Jul 10, 2025

Also in Fortune

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67694 in the federal list. How to read these figures.