Sewer Extension - Main Street
Port Blandford, Newfoundland and Labrador
Federal contribution
$66,174
Federal share33%
of $198.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.6 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Port Blandford
- Construction start
- Sep 23, 2008(actual)
- Construction end
- Feb 28, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 1, 2008
- Construction end18 months lateforecast Sep 1, 2009