New Earth Dam and Dykes Noseworthys Pond
Port Blandford, Newfoundland and Labrador
Federal contribution
$76,993
Federal share33%
of $234.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 15, 2008
20082009201020112012
Built
Approved 6 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Port Blandford
- Construction start
- Sep 17, 2007(actual)
- Construction end
- Dec 31, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 1, 2007
- Construction end3.6 years lateforecast Jun 1, 2008
Also in Port Blandford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16524 in the federal list. How to read these figures.