Retrofit Sewage Lift Stations, #2 & #4
Port Blandford, Newfoundland and Labrador
Federal contribution
$50,999
Federal share28%
of $182.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Port Blandford
- Construction start
- Jun 30, 2009(actual)
- Construction end
- May 31, 2010(actual)
Against the original forecast
- Construction start3 months earlyforecast Oct 1, 2009
- Construction end7 months lateforecast Oct 31, 2009