Water Distribution and Wastewater Collection System Rehabilitation

North Battleford, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$250,000
Federal share16%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 24, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of North Battleford
Construction start
Aug 16, 2006(actual)
Construction end
Dec 12, 2007(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2006
  • Construction end13 months lateforecast Oct 31, 2006