Centennial Park Activities Centre

North Battleford, Saskatchewan

completeRecreationMRIF
Federal contribution
$56,947
Federal share25%

of $227.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 1, 2008
20082009
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of North Battleford
Construction start
Dec 14, 2007(actual)
Construction end
Jan 22, 2009(actual)

Against the original forecast

  • Construction end2 months earlyforecast Mar 31, 2009