City of North Battleford Primary Sanitary Sewer Upgrades

North Battleford, Saskatchewan

completeWastewaterNRP
Federal contribution
$4.5M
$4,533,333
Federal share33%

of $13.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 26, 2019
20192020202120222023
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of North Battleford
Construction start
Jun 15, 2021(actual)
Construction end
Apr 30, 2023(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 1, 2021