Water and Sewer McAuley Lane and Second, Forth, and Park Avenues
Irishtown-Summerside, Newfoundland and Labrador
Federal contribution
$132,081
Federal share33%
of $396.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2007
200720082009
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Irishtown-Summerside
- Construction start
- Dec 19, 2006(actual)
- Construction end
- Sep 30, 2009(actual)
Against the original forecast
- Construction start4 months earlyforecast May 1, 2007
- Construction end22 months lateforecast Dec 1, 2007
Also in Irishtown-Summerside
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14957 in the federal list. How to read these figures.