Water system analysis and intake upgrades

Irishtown-Summerside, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$181,366
Federal share50%

of $362.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Aug 22, 2018(actual)
Construction end
Jul 30, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast Aug 15, 2017
  • Construction end8 months lateforecast Nov 30, 2019

Also in Irishtown-Summerside

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47031 in the federal list. How to read these figures.