Summerside South End Sewer Phase 2

Irishtown-Summerside, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$187,350
Federal share40%

of $468.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 16, 2020
202120222023
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 18, 2022(actual)
Construction end
Jul 31, 2023(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 23, 2022
  • Construction end4 months earlyforecast Dec 1, 2023

Also in Irishtown-Summerside

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56892 in the federal list. How to read these figures.