Water and Sewer Upgrade – High Street

Deer Lake, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$189,012
Federal share33%

of $567.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 15, 2007
2008
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Deer Lake
Construction start
Oct 29, 2007(actual)
Construction end
Oct 28, 2008(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 15, 2007
  • Construction end11 months lateforecast Nov 15, 2007