Schedule
Announced and approvedOct 10, 2006
200720082009
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of North Rustico
- Construction start
- Oct 20, 2006(actual)
- Construction end
- Jul 26, 2009(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 3, 2006
- Construction end2.7 years lateforecast Nov 30, 2006