Kinkora Sewer Main Replacement - 2007
Federal contribution
$36,394
Federal share31%
of $118.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2006
20072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of Kinkora
- Construction start
- Sep 1, 2007(actual)
- Construction end
- Jun 1, 2008(actual)
Against the original forecast
- Construction start10 months lateforecast Nov 1, 2006
- Construction end6 months lateforecast Nov 29, 2007