Community of Kinkora - New Subdivision

Kinkora, Prince Edward Island

completeWastewaterCC
Federal contribution
$109,948
Federal share33%

of $329.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Community of Kinkora
Construction start
Sep 14, 2010(actual)
Construction end
Dec 15, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast May 15, 2010
  • Construction end2 months lateforecast Oct 10, 2010

Also in Kinkora

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22324 in the federal list. How to read these figures.