Concrete Sewer Main Replacement

Kinkora, Prince Edward Island

completeWastewaterCC
Federal contribution
$53,806
Federal share29%

of $183.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Community of Kinkora
Construction start
Sep 30, 2009(actual)
Construction end
Oct 12, 2009(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 17, 2009
  • Construction end3 weeks earlyforecast Oct 30, 2009

Also in Kinkora

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26436 in the federal list. How to read these figures.