Concrete Sewer Main Replacement
Federal contribution
$53,806
Federal share29%
of $183.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Community of Kinkora
- Construction start
- Sep 30, 2009(actual)
- Construction end
- Oct 12, 2009(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 17, 2009
- Construction end3 weeks earlyforecast Oct 30, 2009
Also in Kinkora