Church Street Water Main Extension

Tignish, Prince Edward Island

completeDrinking WaterMRIF
Federal contribution
$41,781
Federal share33%

of $128.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Community of Tignish
Construction start
May 14, 2007(actual)
Construction end
Sep 22, 2008(actual)

Against the original forecast

  • Construction start7 months lateforecast Oct 9, 2006
  • Construction end15 months lateforecast Jun 29, 2007

Also in Tignish

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15650 in the federal list. How to read these figures.